1 · Products (107 available)

Free sample · full data for 2-Ethylhexanol

CAPEX Calculator

2-Ethylhexanol

Run what-if scenarios on total plant capital using the scale-factor (six-tenths) rule; split follows each reference case's ISBL/OSBL/Other/Working-capital ratios.

Step 1 · Process & Location

1 reference cases

Process (multi-select)

Location (multi-select)

Step 2 · Target Capacity & Assumptions

Target capacities (ktpa)

Total = Base Total × (Target / Base Capacity)^0.6

AI Insights

Updated 10/19/2026 · refreshed weekly

Summary

CCM Intel's CAPEX module records a 100 kt/y 2-Ethylhexanol (2-EH) plant on the US Gulf Coast using Davy and Dow LP Oxo technology, with a 2006 investment of USD 95.6 million. That equates to USD 0.956 million per kt of capacity, a 2006-vintage benchmark that is now 20 years old.

Key Highlights

›Total CAPEX: USD 95.6 million for the single reference project in the dataset.

›Capital intensity: USD 0.956 million per kt (about USD 956 per tonne of annual capacity).

›Scale: 100 kt/y nameplate capacity, a mid-sized world-scale oxo-alcohol unit.

›Technology and location: Davy and Dow LP Oxo (low-pressure oxo, rhodium-catalyzed hydroformylation) at USGC, which benefits from integrated propylene and syngas supply.

›Time series: The dataset has only one data point (2006), so no CAGR or year-on-year change can be derived. The figure should be treated as a nominal, historical reference rather than a current cost estimate.

Drivers & Risks

›Driver: USGC feedstock integration (propylene, syngas) and mature LP Oxo technology support relatively low capital intensity.

›Risk: Applying 2006 nominal costs to 2026 projects would likely understate today's costs, given engineering, equipment, and labor cost inflation since then.

›Risk: A single-project benchmark limits statistical robustness. Site-specific factors such as scope, battery limits, and the degree of integration may distort comparisons.

Scenarios

1

Lowest total capital

95.6USD mn

Highest total capital

95.6USD mn

Step 3 · Estimated Total Plant Capital

USD million, split by component

  • ISBL
  • OSBL
  • Other Project Costs
  • Working Capital
USGC · 100 kt0255075100

Scenario Results

USD million

ProcessLocationBase ktBase yrTarget ktISBLOSBLOther Project CostsWorking CapitalTotalUSD mn/kt
Davy and Dow LP OxoUSGC100200610057.88.716.612.595.60.956
1 rows
1 / 1

Methodology

How estimates are calculated

  • Reference cases come from CCMIntel's capital cost database (ISBL, OSBL, Other Project Costs and Working Capital, USD million, cost basis year shown).
  • Total plant capital is scaled with the capacity-exponent rule: Total × (Target ÷ Base capacity)^n, default n = 0.6.
  • The scaled total is split using the original case's component ratios. Optional escalation brings costs from the base year to a target year.
  • Estimates are indicative (±30%) and intended for screening, not for investment decisions.